TL;DR
SoftBank Group reported a ¥1,115.3 billion ($7.0 billion) net loss for July to September 2026, reversing a profit a year earlier. A major contributor was a $3.73 billion loss after a subsidiary changed power-equipment procurement plans for U.S. AI data center projects; the company had paid in advance to secure equipment and manufacturing capacity.
SoftBank Group reported a ¥1,115.3 billion ($7.0 billion) net loss for the July-to-September quarter on November 10, after a subsidiary recorded a ¥597.2 billion ($3.73 billion) loss tied to changes in power-equipment procurement for U.S. AI data center projects. The charge highlights the financial risk of paying ahead for scarce infrastructure before project requirements are settled.
The loss attributable to SoftBank’s owners compares with net income of ¥2,502.2 billion in the same quarter a year earlier. The company’s fiscal year runs from April to March, making the reported period its second quarter of fiscal 2026. SoftBank had reported a profit of ¥347.3 billion in the first quarter, from April through June.
The power-equipment charge comprised ¥457.0 billion ($2.9 billion) in non-refundable advance payments for equipment no longer included in revised plans, and ¥140.2 billion ($0.9 billion) for contract modifications and settlements. SoftBank said cash payments for the contract-related portion were expected from the third quarter onward.
SoftBank said subsidiary Silver Bands 7 had paid ¥1.5 trillion, or $9.48 billion, for equipment and reserved factory capacity through September 30. The payments were made to secure power-generation equipment amid expected shortages. The company said $6.6 billion of the advances remained allocated to equipment for the PORTS-Pike campus in Ohio and other projects. It also cited potential rebates of up to $2.1 billion on future purchases over 10 years, subject to conditions, but did not recognize them as an asset because the amount could not be determined.
SoftBank’s $7 Billion Loss Power costs came into focus
SoftBank reported a quarterly net loss after revising power-equipment plans for U.S. AI data center projects. The charge shows how early infrastructure commitments can carry financial risk when project needs change.
What drove the charge
The subsidiary revised procurement plans as requirements for existing and planned projects changed.
$2.9B in advances
Payments for equipment no longer included in revised plans.
$0.9B in settlements
Costs for contract modifications and settlements.
Why early commitments matter
AI data centers need power systems as well as servers and chips.
- Secure equipment and factory capacity ahead of expected shortages.
- Silver Bands 7 paid in advance for U.S. project needs.
- Changing project requirements led to revised procurement plans.
- Some advances became non-refundable costs.
Projects and possible recovery
The reported plans include the PORTS-Pike campus in Ohio and other projects.
What remains open
SoftBank has not detailed the individual supplier contracts or final recovery outcomes.
- Project financing is expected to help recover the investment, but no amount or timing was specified.
- Potential rebates depend on future purchases and were not recorded as an asset.
- Cash payments for contract-related costs were expected from the third quarter onward.
Power Costs Add Risk to AI Builds
The charge shows how AI infrastructure spending can create losses before data centers are operating. Developers need power generation equipment as well as servers and chips, and SoftBank’s account indicates that securing factory capacity early can leave a buyer exposed when project specifications or procurement plans change.
The loss also matters because SoftBank is both an investor in AI and a backer of infrastructure intended to serve AI demand. The company said it expects to recoup the equipment investment through project financing, but that outcome is not guaranteed in the reported figures. For AI customers, the episode is a reminder that available computing capacity depends partly on the delivery and financing of power systems, not only on access to processors.
The quarter’s result was not caused by the equipment charge alone. SoftBank also reported ¥461.9 billion in finance costs, up from ¥174.7 billion a year earlier, and substantially smaller investment gains than in the comparison quarter. Sales rose to ¥2,215.4 billion from ¥1,916.5 billion, showing that the net loss reflected items below sales rather than a reported decline in revenue.
Products Worth Considering

Dell 32 Plus 4K Monitor S3225QS, 31.5-Inch VA, 120Hz, FreeSync Premium

Samsung 32-inch Odyssey OLED G8 (G80SH) 4K Gaming Monitor

Dell UltraSharp U3225QE 31.5-Inch 4K UHD 120Hz IPS Black Thunderbolt Hub Monitor
As an affiliate, we earn on qualifying purchases.
Advance Orders for U.S. Projects
SoftBank’s financial report says Silver Bands 7, a subsidiary backed by SoftBank and its second Vision Fund, entered manufacturing-capacity reservations, equipment purchase contracts and other arrangements for power-generation equipment. The contracts related to U.S. AI data center projects, including the PORTS-Pike Technology Campus in Pike County, Ohio.
SoftBank’s investor presentation says it made advance investments to secure equipment in anticipation of shortages. It reported payments of $3.9 billion in fiscal 2025 and a further $5.6 billion in the first half of fiscal 2026. The company later said Silver Bands 7 revised its procurement strategy in response to changing requirements for existing and planned projects.
At a Tokyo briefing, Chief Financial Officer Yoshimitsu Goto said intense competition for energy supply and power equipment had prompted purchases before long-term specifications were final, Reuters reported. SoftBank’s results also note that the financial statements are an English translation of the Japanese original and had not been reviewed by auditors.
“Made bridge investments in advance to secure power generation equipment in anticipation of shortages.”
— SoftBank Group investor presentation
Equipment and Recovery Details Pending
SoftBank has not identified the specific equipment involved, the suppliers, or which purchases were cancelled or changed. The company also has not disclosed how the revised requirements differed from the original plans or how much of the $6.6 billion still allocated to projects has been paid to suppliers versus reserved for future purchases.
The potential rebates of up to $2.1 billion are conditional and spread across future purchases over as long as 10 years. SoftBank said it could not determine their amount and did not record them as an asset. The extent to which project financing will recover the remaining investment, and when that financing might be secured, was not specified in the supplied report.
The reported quarterly results were unaudited, according to SoftBank’s presentation. The company’s disclosures establish the charge and its stated cause, but do not provide enough detail to independently assess the terms of individual supplier contracts or the final cost of the broader data center plans.
Project Financing and Q3 Payments
SoftBank said it expects to recoup the investment through project financing, while cash payments related to contract modifications and settlements were expected from the third quarter onward. The next results and company disclosures may clarify the payments made, financing secured and equipment still assigned to PORTS-Pike and other projects.
Investors and AI infrastructure customers will also be watching whether SoftBank’s revised equipment requirements lead to further charges or delays. The company has not provided a timeline for completing the procurement changes or a confirmed value for any future rebates, so those outcomes remain open.
Key Questions
Why did SoftBank report a $7 billion quarterly loss?
SoftBank reported a ¥1,115.3 billion ($7.0 billion) net loss for July to September 2026. A ¥597.2 billion ($3.73 billion) loss tied to changes in power-equipment procurement was a major contributor. Higher finance costs and smaller investment gains than a year earlier also affected the result.
What caused the power-equipment charge?
SoftBank said subsidiary Silver Bands 7 revised its procurement strategy as the requirements of existing and planned U.S. data center projects changed. The charge included $2.9 billion in non-refundable advances for equipment no longer in the plans and $0.9 billion for contract modifications and settlements.
How much had SoftBank paid in advance?
Through September 30, 2026, Silver Bands 7 had paid ¥1.5 trillion, or $9.48 billion, for power-generation equipment and reserved factory capacity, according to SoftBank.
Could SoftBank recover some of the cost?
SoftBank said it expects to recoup the investment through project financing. It also cited potential rebates of up to $2.1 billion on future equipment purchases, subject to conditions. The company did not recognize the rebates as an asset because their amount could not be determined.
Which projects were affected?
SoftBank named U.S. AI data center projects, including the PORTS-Pike Technology Campus in Ohio. It has not disclosed which specific equipment orders or suppliers were involved, or which purchases were cancelled.